Case Study House #1.16:  We Have a Driveway

Case Study House #1.16:  We Have a Driveway

by Makers1 | May 6, 2015 | BUILD, Case Study House #1, PROJECTS

Yesterday was one of those days where progress was made all over!      Our excavator, Rusty, did our final grading and spread out our base gravel for our driveway We passed our insulation and mechanical system inspections We finished all of the final...
Case Study House #1.15 A Long Winter

Case Study House #1.15 A Long Winter

by Makers1 | May 4, 2015 | BUILD, Case Study House #1

I figure with the sun now shinning and our temps up above 70 everyday now…it’s a beautiful time for a project update. Photo looking up from the front entry, Oliver, Isabel and Sawyer hanging out office window:    Unfortunately the winter...

CASE STUDY HOUSE #1.14: Housewrap for the Christmas Present!

by Makers1 | Dec 29, 2014 | BUILD, Case Study House #1, PROJECTS

  We were SO close to getting the house all wrapped up for Christmas!  The structure of the main house is now 100% wrapped with just 2 sides of the garage that need to be covered. I need to get a final photo of the house completely wrapped – but, I’m...
CASE STUDY HOUSE #1.12: Wall construction

CASE STUDY HOUSE #1.12: Wall construction

by Makers1 | Oct 13, 2014 | BUILD, Case Study House #1, PROJECTS

We’re starting to see some real progress moving along! So much so, that a neighbor stopped by while I was working the other day and said…”Oh, now I get it!”… Little do they know… They still have no idea what it will look like! The...
CASE STUDY HOUSE #1.11: Open Tread Stair Design

CASE STUDY HOUSE #1.11: Open Tread Stair Design

by Makers1 | Oct 12, 2014 | BUILD, Case Study House #1

I’ve been playing with several ideas for the stairs at CSH1.0 (Case Study House 1.0). We definitely want to continue the theme of “open and airy” on the interior – so an open tread stair design was almost a given. But, having never designed or...
CASE STUDY HOUSE #1.10: Foundation progress!

CASE STUDY HOUSE #1.10: Foundation progress!

by Makers1 | Sep 25, 2014 | BUILD, Case Study House #1, PROJECTS

Quick photo gallery update showing the current progress. The basement was excavated and the foundation footings poured. Then came the basement walls with window and door openings (luckily Steve was on site and caught them missing 2 windows that I had clearly marked...
« Older Entries
Next Entries »

Recent Posts

  • Current Work – update 12/2017
  • Case Study House: 1.21: Continual Progress – Kids room lofts
  • SEASONS GREETINGS! Bywater’s 2015 Christmas Video
  • Case Study House: 1.20: A Year of Progress
  • Case Study House: 1.19: moving INSIDE…tile work!

Recent Comments

    Archives

    • December 2017
    • January 2017
    • January 2016
    • September 2015
    • July 2015
    • May 2015
    • December 2014
    • November 2014
    • October 2014
    • September 2014
    • August 2014
    • July 2014
    • June 2014
    • May 2014
    • April 2014

    Categories

    • Architecture
    • BLOG
    • BUILD
    • Case Study House #1
    • DESIGN
    • Process
    • PROJECTS
    • Uncategorized

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org
    MAKE DESIGN + BUILD ©2020